Žito – Slovenia

Project statistics

Annual savings

1,700

MWh

Gas consumption reduced by

50

%

Situation before the contract and client requirements

Before reconstruction, the client had an over-dimensioned steam system, operating inefficiently with a very poor yield.

The client had low pressure process steam, and no return of condensate.

The client wanted to decrease costs and increase system efficiency.

Resalta solution

Resalta provided solutions in heat recovery, steam for industrial usage, engineering and issued a savings warranty.

Resalta installed two new steam boilers carefully adapted to the actual needs of Žito Maribor, including a system for the heat recovery of flue gases.

Resalta monitors the system through Resalta‘s central control system (web access) in real time.

Повече информация?

Свалете подробности за осъществени проекти.

Общи правила и условия.

Абонирайки се за нашия бюлетин, се съгласявате да получавате на електронната си поща съобщения от Резалта д.о.о. Целта на бюлетина е да информира посетителите на интернет страницата ни, нашите партньори, клиенти и широката общественост за дейността на Резалта, новите ни проекти, развития, предстоящи събития, както и новини във връзка с енергийната ефективност и възобновяемите източници. Публикуваме бюлетина най-често веднъж месечно, като са възможни изключения при непредвидени, но важни новини. Запазваме си правото да променим или спрем да издаваме бюлетина по всяко време и без предварително да ви информираме. Поверителността на вашата информация е много важна за нас и никога няма да я предоставим или продадем на трети страни. Имате възможност да прекратите абонамента си за бюлетина по всяко време.