Novigrad Municipality – Croatia

Project statistics

yearly reduction in energy use

307,411

kWh

Annual savings

35,600

EUR

115.5

t

annual reduction of CO2 emissions

Situation before the contract and client requirements

The municipality of Novigrad in Istria announced a public tender for the renovation of all their public lighting according to the ESCO model.

One of the key requirements was to preserve the unique architectural appearance of the city, for the luminaires to match the style of the town.

Resalta solution

Replacement of 954 luminaires with 860 LED luminaires.
The old luminaires had an installed capacity from 70 to 400 W,

Resalta replaced them with more energy efficient luminaires ranging from 19 to 109 W.

The contract duration is 7.5 years. A year into the contract, the savings made by Novigrad already exceeded expectations and initial calculations. 

Повече информация?

Свалете подробности за осъществени проекти.

Общи правила и условия.

Абонирайки се за нашия бюлетин, се съгласявате да получавате на електронната си поща съобщения от Резалта д.о.о. Целта на бюлетина е да информира посетителите на интернет страницата ни, нашите партньори, клиенти и широката общественост за дейността на Резалта, новите ни проекти, развития, предстоящи събития, както и новини във връзка с енергийната ефективност и възобновяемите източници. Публикуваме бюлетина най-често веднъж месечно, като са възможни изключения при непредвидени, но важни новини. Запазваме си правото да променим или спрем да издаваме бюлетина по всяко време и без предварително да ви информираме. Поверителността на вашата информация е много важна за нас и никога няма да я предоставим или продадем на трети страни. Имате възможност да прекратите абонамента си за бюлетина по всяко време.